The finishing block upgrade, Phase 3 of the multi-phase upgrade was successfully completed at the end of 2017. Russula was responsible for installation supervision, commissioning, on-site operator/maintenance training and provided both on-site and off-site remote support after the start-up to guarantee a smooth transition back to production.
Since Russula is an independent systems integrator, Evraz was offered two drive alternatives from different suppliers. The 6.8 MW ABB Mega Drive-LCI was chosen. It is a robust medium voltage drive used for high power applications ideal for the finishing block.
During an 11-day maintenance outage, the new drive was installed and commissioned. The finishing block successfully returned to operations on December 8, 2017.
Esta página utiliza cookies propias con finalidad técnica y funcional y cookies de terceros con finalidad publicitaria. Para consentir su utilización y confirmar que ha leído la información proporcionada pulse el botón aceptar. Podrá conocer cómo gestionar o deshabilitar las cookies en configurar cookies.